Villa handover in Dubai: a snagging checklist that actually works

Family lounge in a newly handed-over villa

Handover day is emotional, and that is exactly why it needs a checklist. Snagging is the inspection where you list every defect, unfinished item and scratch before you accept the villa. It is far easier to have something fixed while the contractor's team is still on site than six weeks after you have moved your furniture in.

Before the inspection

  • Ask for the villa to be cleaned and for power, water and AC to be running. You cannot test what is switched off.
  • Bring the approved drawings and the finishes schedule, so you check against what was agreed and not against memory.
  • Bring a phone charger or socket tester, a small ball or marble, masking tape, and someone to write while you look.
  • Go in daylight, and allow several hours. Then come back once after dark for the lighting.

Room by room

Floors, walls and ceilings

Look along surfaces at a low angle, not straight at them. Check for hollow-sounding tiles by tapping, uneven grout lines, cracks, paint patches that do not match, and stains on ceilings - a ceiling stain is a leak until proven otherwise.

Doors, windows and joinery

Open and close every door, window, drawer and wardrobe. They should latch without force and not swing by themselves. Check locks, keys, seals, mosquito screens and that sliding doors run freely. Look inside wardrobes, not just at the doors.

Electrical

Test every socket and every switch. Check the distribution board is labelled so you know which breaker serves which room. Test the doorbell, intercom, gate motor and external lights.

Plumbing and wet areas

Run every tap, hot and cold, and flush every toilet. Fill basins and watch them drain. Pour water on bathroom and balcony floors: it should run to the drain, not sit in a corner. Roll the ball across the floor to see which way it really falls. Look under sinks for drips and check the water heaters and pumps.

Air conditioning

Run every unit for long enough to cool the room. Listen for rattles, check each thermostat controls the right room, and look for water marks around grilles and access panels.

Outside

Check paving falls away from the house, the boundary wall and gates, the roof (outlets clear, no ponding), external taps, drainage covers, and the pool equipment if there is one.

The documents to collect

  • The completion certificate and utility connection papers.
  • As-built drawings, especially for electrical, plumbing and drainage routes.
  • Warranties and manuals for AC, water heaters, pumps, waterproofing, kitchen and appliances.
  • Inspection and test records. On our projects, clients receive the photographed, signed records of concealed work at handover.
  • All keys, remotes, access codes and the contact for defects reporting.

Writing the snag list

Number every item, note the room, describe the defect in one line and photograph it. Mark the spot with masking tape. Agree a date for completion and re-inspect against the same list - an item is closed when you have seen it fixed, not when you are told it is. Keep the list; it is your record if the same fault returns.

After you move in

Some defects only appear in use: a door that binds in summer humidity, a slow drain, an AC unit that struggles in August. That is what the defects liability period in your contract is for. Report each problem in writing with a photo, as it appears, rather than saving them for one long list at the end. How that period works, and the separate ten-year structural liability under UAE law, is covered in our contract checklist.

Planning a villa and want to see what a finished handover looks like? Visit the gallery, or talk to us about your project.

Frequently asked questions

What is snagging in villa construction?

Snagging is the inspection carried out before you accept a villa, where every defect, unfinished item and cosmetic flaw is listed for the contractor to fix. Each item should be numbered, described, photographed and re-inspected once repaired.

How long does a villa snagging inspection take?

Allow several hours in daylight for a full villa, plus a second short visit after dark to check lighting. Rushing the inspection is the most common reason defects are missed.

What documents should I receive at villa handover?

The completion certificate and utility connection papers, as-built drawings, warranties and manuals for installed equipment, inspection and test records, and all keys, remotes and access codes.

What if I find a defect after moving in?

Report it in writing with a photograph as soon as it appears. Defects found during the contract's defects liability period are the contractor's to repair; serious structural defects are also covered by the ten-year liability under UAE law.